MDC

Tuesday, June 16

Posted on

Load out boom sections and bring to The Hartford. Load trailer to return equipment to yard. Cut piles.

Friday June 12

Posted on Updated on

Picked up trailer early in the yard. Brought 28B to The Hartford and unloaded there. Loaded long piles from MDC and brought to the yard and unloaded.

Thursday June 11

Posted on Updated on

WP_20150611_001Completed driving remaining piles. Cut piles and load dumpsters.

Wednesday June 10

Posted on Updated on

Impact 13 piles on North road. Stage hammers and walk crane back to center of job site. Ready to vibrate the remaining piles tomorrow.

Tuesday June 9

Posted on Updated on

Light went on at 6:30. Cut all piles that have elevations. Left at 11:30.

Monday June 8

Posted on Updated on

Drove 13 piles from the North Road.WP_20150608_001 WP_20150608_002

Friday June 5

Posted on Updated on

Hammer 45 piles. Move crane to north td

Thursday june 4

Posted on Updated on

Vibrating piles, 22 completed.

Wednesday June 3

Posted on Updated on

Tuned up piles and dieseled them in screens building. Light was on for 30 minutes at 8:30. Began vibrating production piles. Ape hammer down at 11am. Switched to 28b and continued. 21 vibrated to rock.

Tuesday, June 2

Posted on Updated on

Light is on at 6:30. Loaded trailer with cutoffs and small power pack we didn’t use. Cut all piles that are marked. 10 am light is off. Tuned up 2 piles in screens building. Impacted 24 piles. Walked back into sc area, tuned up two.